A crane may be on site, fuelled, inspected and ready to work, but that does not automatically mean it is ready to lift. The question of when should cranes be operated comes down to whether the lift can be carried out under the conditions set out in the plan, with the right people, equipment and controls in place. If one of those conditions changes, the operation may need to pause.
For site managers and contractors, this is not paperwork for paperwork’s sake. A well-timed, controlled lifting operation protects people, prevents damage, keeps programmes moving and avoids the cost of a failed or delayed lift. Whether you are using a HIAB for machinery placement, materials delivery or a more complex planned lift, the same principle applies: operate only when the site is genuinely ready.
When should cranes be operated?
Cranes should be operated only after the lift has been properly planned, the equipment has been selected and checked, the ground has been assessed, and a competent lifting team is in place. The lift must also remain within the crane manufacturer’s limits, including its load chart, working radius and wind restrictions.
In the UK, lifting operations are governed by the Lifting Operations and Lifting Equipment Regulations 1998, commonly known as LOLER. These require lifting operations to be properly planned by a competent person, appropriately supervised and carried out safely. The Provision and Use of Work Equipment Regulations 1998 also apply to the safe use and maintenance of work equipment.
The timing of the lift therefore depends on more than the delivery slot. It depends on site conditions at that moment. A crane that was safe to operate at 8am may not be safe at 2pm if wind has increased, ground has softened, access has been blocked or another contractor has entered the lifting zone.
Start with a lift plan that reflects the real job
The lift plan should be proportionate to the task. A straightforward, repetitive lift may need a simple plan and clear method of work, while a complex lift may require more detailed engineering input, specific controls and closer supervision. What matters is that the plan reflects the actual load, location and site constraints rather than a generic description of the work.
Before operating, the appointed person or competent planner should establish the load weight, dimensions, centre of gravity, lifting points and destination. They must also consider the crane’s configuration, outrigger positions, radius, slew path and any obstructions. A load that is light enough at one radius can exceed the crane’s capacity when placed a few metres further away.
The plan should identify the lifting team and their responsibilities. This usually includes the crane operator, slinger/signaller and a person with overall responsibility for planning the lift. Everyone involved needs to understand the agreed signals, exclusion zone and stop-work process before the first lift begins.
Check the crane, lifting accessories and certification
A crane should not be operated until its pre-use checks have been completed and any defects have been addressed. The operator needs to confirm that the machine is suitable for the planned work, correctly configured and functioning as intended. This includes safety devices, controls, outriggers, indicators and emergency systems.
Lifting accessories deserve the same attention. Chains, slings, shackles, spreader beams and lifting points must be appropriate for the load and free from visible damage. Their safe working load must suit the planned lifting arrangement, not merely the total weight of the item. Sling angles, for example, can significantly increase the force applied to each leg of a sling.
Thorough examination records should be current where required. A current certificate does not remove the need for a visual pre-use check, however. If equipment has been damaged in transit, altered, overloaded or exposed to conditions that could affect its safety, stop and seek competent advice.
Ground conditions can decide whether the lift goes ahead
Poor ground is one of the quickest ways for a routine lift to become a serious incident. Outriggers transfer substantial loads into a relatively small area, so a surface that appears firm may not provide adequate support. Tarmac, paving, made-up ground, drainage runs, cellars, service trenches and recently excavated areas all require careful consideration.
The crane should be positioned only when the ground bearing capacity has been assessed for the planned setup. Suitable mats or spreader pads may be necessary to distribute outrigger loads. They must be correctly sized, in sound condition and placed on stable ground, not used as a quick fix for an unsuitable location.
Ground conditions can change during a project. Heavy rain, excavation work, leaking services and repeated vehicle movements can reduce support beneath a crane. If there is uncertainty about what lies below the setup area, do not rely on visual judgement alone. Confirm the information before lifting.
Weather matters, but wind speed is not the only issue
Wind limits are often the first weather consideration, particularly when handling large panels, cladding, glazing, steelwork or awkward loads with a high surface area. The permitted wind speed must come from the crane manufacturer’s instructions and the lift plan, taking account of the specific load. A large, light load can become difficult to control well before a crane reaches its maximum lifting capacity.
Conditions should be monitored throughout the operation, not checked once at the start of the shift. Gusting wind, changing wind direction and wind funnelled between buildings can all affect the load. Rain can reduce visibility and make access surfaces slippery, while lightning, fog, ice and poor light may require work to be postponed.
The right decision is not always to cancel the day’s lifting. It may be possible to change the sequence, reduce the radius, use a more suitable machine or wait for a safe weather window. That decision must be made by the responsible competent people, not driven solely by programme pressure.
Keep people and other site activity out of the risk area
A crane should be operated only when the lifting area is controlled. The landing zone, travel path and area beneath any suspended load should be kept clear of people who do not need to be there. Barriers, cones, banksmen and clear communication all have a role, but the exact controls should suit the site layout and the public or workforce exposure.
Never plan for people to work beneath a suspended load. Loads should be guided where necessary using suitable tag lines, without putting the slinger/signaller in a position where they could be struck, trapped or pulled into the load path. The operator must have a clear method of communication with the signaller and should stop immediately if signals are unclear or lost.
Busy sites also demand coordination. Deliveries, mobile plant, pedestrians, access-platform work and road closures can affect the lift. A short delay to secure the area is usually far less disruptive than stopping work after an incident.
Know when to stop and reassess
The safest lifting teams do not treat a stop as a failure. They treat it as part of competent operation. Work should pause when the plan no longer matches site reality, such as when the load weight is uncertain, the route is obstructed, wind conditions deteriorate, the ground shows movement or an unexpected service is found.
Stop as well if there is a change of personnel without a proper handover, a fault warning on the crane, damage to lifting accessories or a communication problem between the operator and signaller. The lift should restart only after the issue has been assessed and the responsible person is satisfied that controls remain effective.
For complex or higher-risk work, a trial lift can be valuable. Lifting the load just clear of the ground allows the team to confirm balance, sling arrangement, brake function and load stability before committing to the full movement. It takes little time and can reveal problems that are not obvious during planning.
Choose operated hire when control and accountability matter
For many contractors, operated crane hire provides a practical way to bring the right machine and competent operator to site without managing specialist lifting resources in-house. It is particularly useful where access is tight, lifting is time-critical or the site team needs guidance on setup, reach and machine selection.
JBL Group supplies modern lifting equipment with certified operatives and practical project support across London and the South of England. Early discussion helps identify whether a HIAB, alternative lifting arrangement or access solution is suitable before the machine arrives on site.
A crane should operate when the plan, people, machine and conditions all align. If they do not, pausing to put them right is not lost time – it is how a dependable lifting operation stays safe and keeps the wider job moving.